We continue our trip to Lake Baikal as part of parliamentary control of the national project “Preservation of Lake Baikal“, Tran

We continue our trip to Lake Baikal as part of parliamentary control of the national project “Preservation of Lake Baikal“, Trans-Baikal Territory. [1] Tarbagatai village, construction of treatment facilities, capacity - 50 cubic meters/day. Cost of the object: 54 million rubles. Implementation period: December 18, 2020 - November 15, 2022. The backlog is more than 700 days. Comments identified during construction control are not eliminated in a timely manner; a significant part is not eliminated for a long time. [2] n.p. Khilok, reconstruction of treatment facilities. Capacity - 1500 cubic meters/day. Cost of the object: 301 million rubles. Implementation deadline: January 11, 2021 - November 15, 2022. The backlog is more than 700 days. The strength of reinforced concrete structures in facilities for the treatment of domestic wastewater does not correspond to the design. Comments are not corrected in a timely manner, and a significant portion are not corrected for a long time. [... Source: Lord Of War
Back to Top