Micro Hydro Electric Power System in Colorado Part 9

Construction - Part 2. Weir diversion is constructed with diversion of water by use of temporary dam. Footings for pipe bridge are installed. An early arrival of Winter brings an end to construction for this Diversion, Weir intake, Pipe bridge, Powerhouse slab are all well will return in the Spring.